UC Riverside, Library, Water Resources Collections and Archives > Clearinghouse for Dam Removal Information (CDRI) > 90-day Post-Breach Preliminary Sediment Behavior Report-Condit Dam Removal

Text / 90-day Post-Breach Preliminary Sediment Behavior Report-Condit Dam Removal

Have a question about this item?

Item Information.

Title
90-day Post-Breach Preliminary Sediment Behavior Report-Condit Dam Removal
Creator
Riverbend Engineering and Jr Merit Industrial Contractors
Date Created and/or Issued
12/18/12
Contributing Institution
UC Riverside, Library, Water Resources Collections and Archives
Collection
Clearinghouse for Dam Removal Information (CDRI)
Rights Information
Copyrighted
Transmission or reproduction of materials protected by copyright beyond that allowed by fair use requires the written permission of the copyright owners. Works not in the public domain cannot be commercially exploited without permission of the copyright owner. Responsibility for any use rests exclusively with the user.
Description
Scope/Content: Abstract: This document is a preliminary sediment behavior report and has no abstract. This document covers: post reservoir dewatering sediment behavior, remaining sediments in the former reservoir area and continuing sediment management activities.
Scope/Content: Dam type: gravity
Scope/Content: Date constructed: 1913. Date removed: 2011.
Type
text
Identifier
ark:/86086/n2rr1xv4
1232
Language
eng
Subject
Legal and policy
Pre- and post-project monitoring
Sediment and channel dynamics
Dams
Dam retirement
Place
White Salmon River, WA
Condit Dam